QAWork and Time

Work and Time: Efficient Methods

Basic Concept

  • Work = Rate × Time
  • If A completes work in n days, A's one day work = 1/n

Combined Work

  • If A does work in a days and B in b days:
  • Combined rate = 1/a + 1/b
  • Time together = ab/(a+b)

Work and Wages

  • Wages ratio = Work ratio = Efficiency ratio
  • If A and B work for different times: Wages ratio = (Efficiency × Time) ratio

Pipes and Cisterns

  • Inlet pipe: Positive work
  • Outlet pipe: Negative work
  • Net rate = Sum of all rates

Men-Days Formula

  • M₁D₁W₂ = M₂D₂W₁
  • (Men × Days × Hours/day) / Work = Constant

CAT Strategy

  • Use LCM of days as total work for easier calculations
  • Convert all rates to same time unit
  • For complex problems, use efficiency ratios